[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

dam-l Epupa Verdict Delayed/LS



>>From owner-irn-safrica@igc.org  Fri Jul 10 19:54:48 1998
>Return-Path: <owner-irn-safrica@igc.org>
>Date: Fri, 10 Jul 1998 14:45:59 +0100
>From: lori@irn.org (Lori Pottinger)
>Sender: owner-irn-safrica@igc.org
>Subject: Epupa Verdict Delayed/LS
>To: irn-safrica@igc.apc.org
>X-Sender: lori@pop.igc.apc.org
>
>>From The Namibian, July 10. 1998:
>
>
>       Epupa verdict delayed
>
>       Commission says report 'deficient'
>
>       CHRISTOF MALETSKY
>
>       THE official decision on the construction of the controversial Epupa
>       hydropower project has been postponed for one month after a two-day
>       meeting of the Namibia-Angola Permanent Joint Technical Commission
>       (PJTC) found the draft feasibility study incomplete.
>
>       A statement issued by the joint chairmen of the PJTC, Siseho Simasiku
>       (Namibia) and Armindo Gomes Da Silva (Angola), Thursday said the
>       meeting found that the study contained some deficiencies that must be
>       amended before the report is finalised to meet all the requirements of
>       the terms of reference.
>
>       "The major shortcomings relate to the incomplete consideration of
>       mitigation measures, the lack of a complete proposal for an
>       environmental management and post-construction monitoring plan,
>       inconclusive work performed on the bilateral agreement and the
>       non-inclusion of the terms of reference for the phase three work," the
>       statement said.
>
>       The study contained comments on the project by Supervision Committee
>       for the Feasibility Study (SCFS), and other organisations such as the
>       World Conservation Union (IUCN) and the Norwegian Water and
>       Energy Administration Directorate (NVE) which were specifically
>       requested by the PJTC to review the draft report.
>
>       Phase three of the three-year study was the controversial inclusion of
>       the Epupa site - seen as "prestige project" - after the Namang
>       consortium comprising Namibian, Angolan, Swedish and Norwegian
>       consultants recommended Site E in the Baynes mountains as the only
>       option to be investigated further.
>
>       The decision cost taxpayers of both countries an additional N$3 million
>       which was split between the two governments.
>
>       The Baynes site was seen by Government as too small, despite its
>       environmental and social advantages over the other sites considered. It
>       is some 40 kilometres downstream from the Epupa falls and is
>       considered to have less negative social and environmental impacts than
>       the other sites initially considered.
>
>       In sharp contrast, the Epupa site is seven kilometres downstream from
>       the falls and is likely to displace some 700 Himba people. The area
>       flooded at the Baynes site would be 94sq kilometres while Epupa would
>       cover over 250 sq kilometres.
>
>       The Baynes site is likely to be more dependent on the repair and
>       regulation of Gove dam inside Angola which was damaged during the
>       civil war and has not been regulated since 1975. The consultants
>       pinpointed Baynes as the best option in October 1996.
>
>       Environmentalists have expressed fears that the decision to include the
>       Epupa site indicated that the feasibility study was just a procedural
>       exercise while the political decision to build the dam at Epupa
>itself had
>       already been taken regardless of the consultants' conclusions.
>
>       Thursday the PJTC said it had been agreed that a subcommittee be
>       formed to discuss details with Namang to revise and finalise the report.
>       The subcommittee will be made up of seven officials from the two
>       countries and will start its work with immediate effect. The final
report
>       accommodating all concerns is expected to be ready by the end of next
>       month.
>
>       In addition to the shortcomings, the PJTC had recognised there was a
>       need for the verification of some facts before the project could finally
>       be concluded.
>
>       "With due consideration of the problems indicated above, the PJTC was
>       not in a position to discuss the matter of the selection of the
>single site
>       (Epupa or Baynes) for implementation as envisaged. Instead, this topic
>       has been postponed for discussion and formulation of the final
>       recommendation to the two governments at the next PJTC meeting in
>       Luanda on August 24-25 1998," it said.
>
>       The statement said it also reviewed progress made by several projects
>       including the Calueque dam, Gove dam, technical assistance to the PJTC
>       by Coba-Internel, and bilateral agreements on the Kunene River Basin.
>
>       July 10, 1998
>
>                               CLICK to return to story index
>
>
>               [Front Page] [Namibian News] [Opinions] [Columns] [Economic
>News ] [Sports]
>
>           [Arts] [Oshiwambo] [About The Newspaper] [Email Us ] [Subscribe]
>[Archive] [Web Links]
>
>
>::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
>      Lori Pottinger, Director, Southern Africa Program,
>        and Editor, World Rivers Review
>           International Rivers Network
>              1847 Berkeley Way, Berkeley, California 94703, USA
>                  Tel. (510) 848 1155   Fax (510) 848 1008
>                        http://www.irn.org
>::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
>
>
>
 ><((((º>`·.¸¸.·´¯`·.¸.·´¯`·...¸><((((º>¸.
·´¯`·.¸. , . .·´¯`·.. ><((((º>`·.¸¸.·´¯`·.¸.·´¯`·...¸><((((º>
Dianne Murray,
Coordinator, Dam-Reservoir Working Group
Webmistress, Dam-Reservoir Impact and Information Archive
http://www.sandelman.ottawa.on.ca/dams
vox: 1-613-520-2757  fax:1-613-520-3898	e: dianne@sandelman.ottawa.on.ca
Home of Project Pisces: fish need flow!
><((((º>`·.¸·´¯`·¸><((((º>¸.·´¯`·.¸.><((((º>`·.¸¸.·´¯`¸><((((º>